Ross Road - Danbury Road to Kenn Road

This project will widen the southbound lane of Ross Road from Kenn Road (Springdale) to Danbury Road. The project includes tree removal, curb and gutter, storm sewer, and sidewalk. The work is scheduled for the 2014 construction season. Approximately 900 feet of Ross Road is included in this project. Average daily traffic is about 6000 vehicles per day. Ross Road at Kenn Road will closed for 30 days during the summer months. The OPWC (Ohio Public Works Commission) awarded $100,000 in funding to the City.

Project Information

  • Project Bid: Summer 2014
  • Bid Price: $190,275.14
  • Contractor: Adleta Construction
  • Project Completion: Spring 2015