2025 Annual Overlay

The City’s overlay program is an annual maintenance project that replaces deficient curb and resurfaces old pavement. Each year, streets are selected to be included in this project based on the current condition and age of the pavement. Residents, businesses, and motorists can expect temporary delays and closures as crews perform the necessary work. 

Project Information

  • Curb Contractor: Prus Construction
  • Curb Budget Price: $850,000.00
  • Pavement Contractor: Barrett Paving Materials
  • Pavement Construction Bid: $2,087,064.90
  • Estimated Completion: Fall 2025

 

Streets for this year’s curb and overlay include:

Street Extents
Gray Rd Water Main Patching between John Gray and Monastery/Lake Michigan
Old Gilmore Rd Route 4 to South Gilmore
Seward Rd Route 4 to Mack
Service Dr Seward to Terminus
Delcrest Dr Greenwich to Stonehill
Decrest Ct Terminus to Decrest Dr
Stonehill Dr Terminus to Mack
Weymouth Ct Decrest to Terminus
Greenwich Dr Danbury to Terminus
Braintreet Ct Danbury to Terminus
Nantucket Ct Greenwich to Terminus
Danbury Rd Delcrest to Ross
Danbury Ln Danbury to Terminus
Waterbury Pl Danbury to Terminus
Fall River Ct Danbury to Terminus
New Briton Cr Danbury to Terminus
Lighthouse Dr Route 4 to Roesch
Roesch Blvd Route 4 to Whitmore
Becker Dr Ambassador to Terminus
Crossbow Dr Hunter to Becker
Oak Valley Dr/Ct Terminus to Terminus
Park Meadows Ct Oak Valley to Terminus
Gelhot Dr Pleasant to Terminus
Doris Jane Ave Denison to Wittenberg
Hicks Blvd Nilles to Route 4
Holiday Dr. Hicks to Winton
De Pauw Dr. Oberlin to Terminus
Vassar Ct Oberlin to Terminus
Wesleyan Dr/Ct Wittenberg to Terminus
Wittenberg Dr Nilles to Holiday
Blackwell Dr/Ct Wesleyan to Terminus
Antioch Dr Denison to Hicks
Muhlhauser Rd Route 4 to Corp Limit